Newsletters
2025
ESCR Newsletter – First Half 2025
Key Highlights:
- Major PA1 milestone reached as new East River Park amenities open to the public, including nature exploration, water play, multiuse turf, 6 tennis courts, 2 basketball courts, BBQ areas, and the esplanade.
- Bridge work across PA1 advances with the Corlears Hook Bridge nearing completion and the old E. 10th Street Bridge being removed.
- Phase 2 transition continues with northern park closures, deep sewer work, and buried floodwall installation at Ballfields 7 & 8.
- PA2 flood protection infrastructure fully handed over to NYC DEP for maintenance and operation.
- Parallel Conveyance progressing with deep sewer work, test pits, and utility relocation across all project sites.
2024
ESCR Newsletter – Second Half 2024
Key Highlights:
- Project Area 2 reaches substantial completion, with Murphy Brothers Playground reopening to the community!
- New amenities opened in East River Park, including Ballfields 1 & 2 with access via the Delancey Street pedestrian bridge.
- PA1 progress continues elsewhere, including esplanade paving, installation of Nature Exploration Area features, major tree planting, and microtunneling for upgraded sewer connections.
- Parallel Conveyance begins new deep sewer work, drainage upgrades, and test pile installations across the corridor.
- Call for Art artwork is redisplayed at the E. Houston Street entrance to East River Park.
ESCR Newsletter – First Half 2024
Key Highlights:
- Delancey Street Pedestrian Bridge installed during an overnight closure of the FDR Drive.
- Major PA1 work includes esplanade reconstruction, buried floodwall installation, and continued bridge construction.
- PA2 reaches 3,129 ft of installed floodwall.
- Parallel Conveyance progresses with deep sewer work and water‑main installations.
2023
ESCR Newsletter – Second Half 2023 | Spanish | Chinese (Simplified)
Key Highlights:
- All ESCR‑related areas of Stuyvesant Cove Park reopen!
- PA2 surpasses 2,400 ft of floodwall installed with ten floodgates placed.
- PA1 progress includes fill delivery via barge, bridge construction, synthetic turf installation, and esplanade construction.
- Parallel Conveyance work expands with test pits, utility relocations, and water‑main upgrades.
ESCR Newsletter - First Half 2023 | Spanish | Chinese (Simplified)
Key Highlights:
- Stuyvesant Cove Park (north of E. 20th St.) reopens. Across the project, over 1,600 feet of floodwalls and six floodgates have been installed.
- PA2 sees installation of multiple new floodgates and ongoing Murphy Brothers Playground construction.
- PA1 construction continues with major progress on floodwalls, soil stabilization, wick drains, and retaining wall work.
- The “ESCR to Your School” program is introduced, bringing resiliency themes to the classroom.
2022
ESCR Newsletter – 4th Quarter 2022 | Spanish | Chinese (Simplified)
Key Highlights:
- PA2 marks two years of progress and surpasses 1,400 feet of installed floodwall.
- PA1 progresses with floodwall foundations, soil stabilization, truck‑reducing barge operations, and bridge rebuilds.
- Archaeological discoveries at Corlears Hook include 19th‑century industrial and residential remains.
- BMCR project introduced as next phase of broader Lower Manhattan coastal protection.
ESCR Newsletter – 3rd Quarter 2022 | Spanish | Chinese (Simplified)
Key Highlights:
- Construction advances in PA2, including Murphy Brothers Playground closure and floodwall/floodgate installation.
- PA1 work includes soil stabilization and deep sewer excavation.
- Parallel Conveyance sewer upgrades begin, adding major drainage improvements.
ESCR Newsletter – 2nd Quarter 2022 | Spanish | Chinese (Simplified)
Key Highlights:
- Asser Levy Playground reopens with new resilient amenities!
- PA2 sees continued floodwall progress and restoration at Stuyvesant Cove Park.
- PA1 phased closures ongoing in East River Park as floodwall construction begins along the Greenway and major utility upgrades continue.
- Selected artwork from the Call for Art goes on display.
ESCR Newsletter – 1st Quarter 2022 | Spanish | Chinese (Simplified)
Key Highlights:
- Major closures in East River Park and Greenway for PA1 construction.
- Delancey Street Bridge dismantled, and the temporary bridge at Corlears Hook is discussed.
- First floodgate installed in PA2, along with ongoing floodwall and bulkhead work.
- Community events, hiring sessions, and emergency preparedness resources provided.
2021
ESCR Newsletter – 2nd Quarter 2021 | Spanish | Chinese (Simplified)
Key Highlights:
- Continued utility relocations and pile installation across PA2.
- First floodwall foundations and formwork installed in Stuyvesant Cove Park.
- Community outreach includes hiring events and our first Call for Art.
ESCR Newsletter – 1st Quarter 2021 | Spanish | Chinese (Simplified)
Key Highlights:
- PA2 construction begins with mobilization, site prep, and utility relocations.
- Pile installation started at Stuyvesant Cove Park and Asser Levy Playground.
- Traffic, cyclist, and pedestrian detours implemented throughout the corridor.