Newsletters

Newsletters

2025

ESCR Newsletter – First Half 2025

Key Highlights:

  • Major PA1 milestone reached as new East River Park amenities open to the public, including nature exploration, water play, multiuse turf, 6 tennis courts, 2 basketball courts, BBQ areas, and the esplanade.
  • Bridge work across PA1 advances with the Corlears Hook Bridge nearing completion and the old E. 10th Street Bridge being removed.
  • Phase 2 transition continues with northern park closures, deep sewer work, and buried floodwall installation at Ballfields 7 & 8.
  • PA2 flood protection infrastructure fully handed over to NYC DEP for maintenance and operation.
  • Parallel Conveyance progressing with deep sewer work, test pits, and utility relocation across all project sites.

2024

ESCR Newsletter – Second Half 2024

Key Highlights:

  • Project Area 2 reaches substantial completion, with Murphy Brothers Playground reopening to the community!
  • New amenities opened in East River Park, including Ballfields 1 & 2 with access via the Delancey Street pedestrian bridge.
  • PA1 progress continues elsewhere, including esplanade paving, installation of Nature Exploration Area features, major tree planting, and microtunneling for upgraded sewer connections.
  • Parallel Conveyance begins new deep sewer work, drainage upgrades, and test pile installations across the corridor.
  • Call for Art artwork is redisplayed at the E. Houston Street entrance to East River Park.

ESCR Newsletter – First Half 2024

Key Highlights:

  • Delancey Street Pedestrian Bridge installed during an overnight closure of the FDR Drive.
  • Major PA1 work includes esplanade reconstruction, buried floodwall installation, and continued bridge construction.
  • PA2 reaches 3,129 ft of installed floodwall.
  • Parallel Conveyance progresses with deep sewer work and water‑main installations.

2023

ESCR Newsletter – Second Half 2023 | Spanish | Chinese (Simplified)

Key Highlights:

  • All ESCR‑related areas of Stuyvesant Cove Park reopen!
  • PA2 surpasses 2,400 ft of floodwall installed with ten floodgates placed.
  • PA1 progress includes fill delivery via barge, bridge construction, synthetic turf installation, and esplanade construction.
  • Parallel Conveyance work expands with test pits, utility relocations, and water‑main upgrades.

ESCR Newsletter - First Half 2023 | Spanish | Chinese (Simplified)

Key Highlights:

  • Stuyvesant Cove Park (north of E. 20th St.) reopens. Across the project, over 1,600 feet of floodwalls and six floodgates have been installed.
  • PA2 sees installation of multiple new floodgates and ongoing Murphy Brothers Playground construction.
  • PA1 construction continues with major progress on floodwalls, soil stabilization, wick drains, and retaining wall work.
  • The “ESCR to Your School” program is introduced, bringing resiliency themes to the classroom.

2022

ESCR Newsletter – 4th Quarter 2022 | Spanish | Chinese (Simplified)

Key Highlights:

  • PA2 marks two years of progress and surpasses 1,400 feet of installed floodwall.
  • PA1 progresses with floodwall foundations, soil stabilization, truck‑reducing barge operations, and bridge rebuilds.
  • Archaeological discoveries at Corlears Hook include 19th‑century industrial and residential remains.
  • BMCR project introduced as next phase of broader Lower Manhattan coastal protection.

ESCR Newsletter – 3rd Quarter 2022 | Spanish | Chinese (Simplified)

Key Highlights:

  • Construction advances in PA2, including Murphy Brothers Playground closure and floodwall/floodgate installation.
  • PA1 work includes soil stabilization and deep sewer excavation.
  • Parallel Conveyance sewer upgrades begin, adding major drainage improvements.

ESCR Newsletter – 2nd Quarter 2022 | Spanish | Chinese (Simplified)

Key Highlights:

  • Asser Levy Playground reopens with new resilient amenities!
  • PA2 sees continued floodwall progress and restoration at Stuyvesant Cove Park.
  • PA1 phased closures ongoing in East River Park as floodwall construction begins along the Greenway and major utility upgrades continue.
  • Selected artwork from the Call for Art goes on display.

ESCR Newsletter – 1st Quarter 2022 | Spanish | Chinese (Simplified)

Key Highlights:

  • Major closures in East River Park and Greenway for PA1 construction.
  • Delancey Street Bridge dismantled, and the temporary bridge at Corlears Hook is discussed.
  • First floodgate installed in PA2, along with ongoing floodwall and bulkhead work.
  • Community events, hiring sessions, and emergency preparedness resources provided.

2021

ESCR Newsletter – 2nd Quarter 2021 | Spanish | Chinese (Simplified)

Key Highlights:

  • Continued utility relocations and pile installation across PA2.
  • First floodwall foundations and formwork installed in Stuyvesant Cove Park.
  • Community outreach includes hiring events and our first Call for Art.

ESCR Newsletter – 1st Quarter 2021 | Spanish | Chinese (Simplified)

Key Highlights:

  • PA2 construction begins with mobilization, site prep, and utility relocations.
  • Pile installation started at Stuyvesant Cove Park and Asser Levy Playground.
  • Traffic, cyclist, and pedestrian detours implemented throughout the corridor.