Project Area 1 (PA1) is concentrated in Manhattan's Lower East Side (LES) between Montgomery Street and East 15th Street, including the East River Park. View upcoming East Side Coastal Resiliency (ESCR)-related travel advisories, construction bulletins and notices for the most up-to-date information on closures, detours, and restrictions for Project Area 1 (PA1). Please note, due to unforeseen conditions (weather, field conditions, etc.) it may become necessary to change some scheduled work locations and operations.
PA1 Construction Bulletin - Week of October 31, 2025 
	Anticipated work schedule for 10/31/2025 to 11/15/2025
The locations below refer to numbered areas in the Weekly Bulletin. Please refer to map at the top of this page for a key.
Nightwork: Removal of the Corlears Hook Temporary Bridge | Chinese
	Sunday, November 16th, 2025, from 12:01am to  10:00am
	The removal of the temporary bridge at Corlears  Hook requires overnight work and a full closure of the FDR Drive northbound and  southbound between Exit 2 (Brooklyn Bridge, Manhattan Civic Center) and Exit 5  (E. Houston Street, Williamsburg Bridge). Vehicles should follow all posted  signs and Traffic Enforcement Agents. 
Nightwork: Removal of the  Corlears Hook Temporary Bridge | Chinese
	Sunday, November 16th, 2025, from 12:01am to  10:00am
	The removal of the temporary bridge at Corlears  Hook requires overnight work and a full closure of the FDR Drive northbound and  southbound between Exit 2 (Brooklyn Bridge, Manhattan Civic Center) and Exit 5  (E. Houston Street, Williamsburg Bridge). Vehicles should follow all posted  signs and Traffic Enforcement Agents. 
No Active Advisories in this location, please refer to Weekly Bulletin above for latest activities.
Nightwork: Northern Section of East River Park between E. Houston Street and E. 14th Street
Ongoing until further notice.
Overnight work hours are required for multiple activities occurring within the northern section of East River Park between E. Houston Street and E. 14th Street, including utility work, median demolition, and floodwall construction. Some of these activities can be disruptive and loud. Partial FDR Drive and FDR Drive Service Road closures will be in effect during this time. Please follow detours and all on-site signage to ensure safety. Noise, vibration, and air quality monitors are in place.
Closure of East River Park Track, Esplanade, E 6th Street Bridge, and E. Houston Street Overpass | Chinese
	Beginning September 8, 2025
	Phase 2 construction requires the closure of  the full northern section of East River Park, including the Track and Field  area, esplanade, and park access via the E. 6th Street Bridge and Houston  Street overpass. Please follow onsite signage. Noise and air monitors are in  place. Please visit our website for information on access points and open areas  in the southern portion of the park as of September 5, 2025. 
East River Greenway Closure & Detour Between Montgomery Street & Stuyvesant Cove Park | Chinese 
	Beginning Tuesday, May 27, 2025
	Construction operations in East River Park require the closure of the Greenway, 24 hours/day, 7 days/week. To access East River Park Track & Field area, use entrances at E. 6th Street and E. Houston Street. To access new southern amenities, use the Delancey Street Bridge. Full access plan available on the ESCR website.
Mobilization of Equipment for E. 13th Street Floodwall Construction | Chinese
	Beginning October 5th, 2025
	To facilitate the construction of the E. 13th Street Floodwall, mobilization will begin to take place in the vicinity of E. 13th Street and FDR Drive. Partial FDR Drive lane closures will be in effect during this time. Please follow detours and all on-site signage to ensure safety. Please note that some of these activities will take place at night, and they may be loud and disruptive. Noise & air quality monitors are in place.
Nightwork: ConEd Manhole Work in the Vicinity of E. 10th Street and FDR Drive | Chinese
	Beginning Monday, August 11, 2025, ongoing for about six weeks
	Overnight work hours are required for ConEd manhole construction in the vicinity of E. 10th Street and FDR Drive. Partial FDR Drive and FDR Drive Service Road closures will be in effect during this time. Please follow detours and all on-site signage to ensure safety. Noise, vibration, and air quality monitors are in place.
Sidewalk Closure & Pedestrian Detour: E. 10th Street  at FDR Drive Service Road | Chinese
	Beginning Wednesday, June 18, 2025
	Ongoing for 2-3 months
	Activities related to the removal of the E. 10th Street  Bridge will require the closure of sidewalks on the north side of E. 10th  Street, between the traffic circle and FDR Drive Service Road. Building access  will be maintained at all times. For your safety, please follow all posted  signs and flaggers.
New Access Pattern for Pier 42 & Corlears Hook Ferry | Chinese
	Beginning September 5, 2025
	The Corlears Hook temporary pedestrian bridge will close as early as Friday, September 5, 2025, as the new Corlears Hook Bridge opens. The new bridge provides direct access between East River Park, Corlears Hook Park, Pier 42, and the Corlears Hook Ferry Terminal. The temporary bridge will be removed at a later date (full Advisory to come). 
Opening of Corlears Hook Park, Pedestrian Bridge, and East River Park South Amenities | Spanish | Chinese
	September 5, 2025
	We are pleased to announce the opening of the Corlears Hook Pedestrian Bridge,  Corlears Hook Park flagpole area and additional East River Park Phase 1  amenities, including:
Access East River Park via Pier 42, the Corlears Hook Bridge, or the Delancey Street Bridge
Nightwork: Removal of the  Corlears Hook Temporary Bridge | Chinese
	Sunday, November 16th, 2025, from 12:01am to  10:00am
	The removal of the temporary bridge at Corlears  Hook requires overnight work and a full closure of the FDR Drive northbound and  southbound between Exit 2 (Brooklyn Bridge, Manhattan Civic Center) and Exit 5  (E. Houston Street, Williamsburg Bridge). Vehicles should follow all posted  signs and Traffic Enforcement Agents. 
 Preparation for E. 13th Street Floodwall Construction in East River Park & FDR Drive  | Chinese
	Beginning in Spring 2025
	To facilitate the construction of the E. 13th Street Floodwall, preparatory operations will be taking place in East River Park and on the FDR Drive. Access to portions of the Greenway may be temporarily limited to ensure safety. Partial FDR Drive lane closures will be in effect during this time. Please follow detours and all on-site signage to ensure safety. Please note that some of these activities will take place at night, and they may be loud and disruptive. Noise & air quality monitors are in place. 
See archive Community Advisories and Weekly Construction Bulletins for PA1