Project Checklists for Owner: Storefronts

This section contains a list of questions/tasks to help Owners, who are responsible for hiring professionals to provide compliance with the applicable Construction Codes and other regulations discussed in the Project Guidelines. These assignments should be made prior to beginning any construction activity. If you are unfamiliar with these regulations, you should reference the corresponding detailed section(s) of NYC Construction Code and other regulations referenced in this guide for more information.

Checklists include:

Initial Project Checklist

DO

  • Pre-Project: Hire a Registered Design Professional (Professional Engineer (P.E.) or Registered Architect (R.A.)) to assure your project is Code-compliant.
  • Project Plans: Only a Registered Design Professional can submit construction documents, including drawings and other submissions, to the Department for approval.
  • Asbestos Investigation: Have asbestos investigation performed on site to check for Asbestos Containing Material (ACM) that will be removed or disturbed.
  • Project Work: Hire a licensed trade professional to perform the work. When hiring a licensed professional, have a written contract that includes the Contractor’s company name, address and license number(s).
  • Safety: Verify if the storefront project’s scope of work requires installation of a temporary fence or sidewalk shed for public safety.
  • Post Permit: Ensure permit is posted in a conspicuous place at the work site for the duration of the work.
  • Security Gates: NYC Local Law 75 of 2009 requires that existing security gates be replaced to allow for visibility and security.
  • Energy Code: When the project scope for a storefront includes installation of new windows, replacement of existing windows, and other exterior wall elements such as bricks etc., an energy analysis in compliance with the current NYC Energy Code is required. Historic buildings listed on the State/National Registers of Historic Places are exempt from the NYCECC, however, buildings only in NYC LPC and Districts are not exempt from the NYCECC.
  • DOB: NOW Requirement: Owner must provide their email address to the Department to obtain for correspondence, inspections and final sign-off of the project.
  • Commissioning: If your project requires commissioning, ensure you have a qualified commissioning agent perform the work and if required, file the commissioning report with the Department prior to sign-off.
  • Work Completion: Ensure inspections and sign-offs are performed to close the project permit.

DON’T

  • Work Without a Permit: Do not begin work without a DOB permit. Property owners and the people performing work without a permit may face violations with penalties, court appearances, civil and/or criminal penalties.

Get a printable version.

Prior to Application Approval Checklist

  • Hire a Registered Design Professional (RDP), P.E. or R.A., to consult and finalize scope of work.
  • Provide consent of the project permit application, and authorize the P.E. or R.A. – who is the ‘Applicant of Record’ – to submit project Construction Documents for Department approval.
  • Project approval is required prior to beginning work.<

    *Note:
    The owner is the individual or entity that owns the building/property, or the owner-authorized property management entity that represents the building for which an application is being filed. The Owner of the building/property is ultimately responsible for the project, and their signature/consent is required for submission of the project application by their design professional, and Department approval. The owner may attend plan examination appointments only if accompanied by the applicant or the Filing Representative.
    *

Get a printable version.

Pre-Permit & On-going Project Work Checklist

Pre-Permit

  • Licensed Contractor: Hire NYC Licensed/Registered Contractor to obtain work permit in order to begin work.
  • Special Inspections: If the scope of work requires, hire the required Special Inspection Agency to perform Special Inspections.
  • Notify the Department: Prior to pulling the permit, use the online notification process to provide the name(s) of the SIA(s) contracted to do the Special and/or Progress Inspections.

On-going

  • Site Safety: Property Owners must maintain their properties in a safe condition during the course of work.

Get a printable version.

Project Completion Close-out Checklist

  • Special Inspections: If the scope of work requires, the Special Inspection Agency hired must complete and submit results online to the Department.
  • Department Inspections: Make sure the Contractor has completed all Department of Buildings inspections and has obtained a sign-off of the completed work.
  • Permit Sign-off: Confirm the Contractor has requested and passed a final sign-off inspection required by the Department.