Brooklyn Bridge – Montgomery Coastal Resilience

Newsletters

2025

BMCR Newsletter – First Half 2025

Key Highlights:

  • Nearly half of flip‑up floodgates and a quarter of permanent concrete floodwalls installed across the corridor.
  • Overview of future gate types (roller + swing gates), which will be installed as floodgate alignment extends across South Street.
  • Community-wide Call for Art completed, with student, adult, and senior artwork installed along South Street and the Esplanade.

2024

BMCR Newsletter – Second Half 2024

Key Highlights:

  • A third of the 2,500 feet of flip‑up floodgates installed, along with progress on seepage‑barrier systems beneath them.
  • Construction advanced on the four‑story interceptor gate chamber and its control building, key to interior drainage protection.
  • Final 10% of distribution water main upgrades underway, with trunk main work to follow next year.
  • BMCR launched a Call for Art, with selected pieces to be installed on‑site in spring 2025.

BMCR Newsletter - First Half 2024

Key Highlights:

  • First flip‑up floodgates arrived and installation began, with hydraulic deployment systems designed for extreme storm conditions.
  • Distribution water main replacement reached ~90% completion.
  • Continued work includes utility relocation, floodwall/gate construction, and interceptor gate building progress.
  • Major Greenway detour in place between Dover St. and Catherine Slip due to waterfront construction.

2023

BMCR Newsletter - Second Half 2023

Key Highlights:

  • Construction progressed with floodwall foundations underway near the Brooklyn Bridge.
  • Water‑main replacement along South Street reached ~70% completion, with remaining work scheduled for 2024.
  • Micropile installation advanced (55 of ~730 installed), enabling floodgate foundation construction in tight spaces beneath the FDR.
  • Floodwall mock‑ups prepared for approval, featuring wave‑pattern designs matching ESCR’s floodwalls.

BMCR Newsletter - First Half 2023 | Spanish | Chinese

Key Highlights:

  • Mobilization begins with test pits, site prep, and temporary fencing installed to verify utilities and subsurface conditions.
  • Overview of flood protection designs to be installed under BMCR.
  • Water‑main replacement started along South Street, requiring scheduled service interruptions with advance notice.
  • Construction fencing expanded under the FDR, shifting Greenway access to a temporary shared path.
  • Upcoming work includes utility upgrades and beginning floodwall and floodgate foundation installation.


Back to BMCR Homepage