Design Professional Checklists: Scaffold
Regardless of how the project work is portioned out, administration of the work remains the responsibility of the Registered Design Professional (RDP) who is the Applicant of Record (Applicant) in responsible charge or has verified Code and Zoning compliance of the drawings and installations for the project. Although there may be some specific projects that do not involve architectural or structural work, which may be completed by other professionals, it is important that the RDP maintain control of the entire project.
This section contains a list of tasks that provide compliance with the Construction Codes and other regulations discussed in the Project Guidelines.
Checklists include:
Prior to Application Approval Checklist
- Provide ‘reference only’ documents of legal existing conditions. These will speed up the plan review process for repairs by reducing comments and the number of back forth and checks.
- Show fire-rated walls on all architectural, mechanical, and electrical, which will facilitate the plan review process.
- Based on the project scope of work, include all applicable Special/Progress Inspections and commissioning statement.
- Although the Registered Design Professionals are only required to show the final construction documents, the Applicant of Record should stamp and sign all formal submittals to the Department to demonstrate he/she has exercised responsible charge as required.
Get a printable version.
Pre-Permit & On-going Project Work Checklist
Pre-Permit
Required Documents: Based on scope of work, supporting documents or deferred submittals must be completed in order to obtain a permit. The following may be required:
- DEP, or OER authorization
- Tenant / Occupant Protection Plan
- Mayor Office for People with Disabilities (MOPD)
- MTA Transit Authority approval
- Public Design Commission approval
On-going
Post Approval Amendments: If the approved work has substantive or significant changes, make sure to submit revised drawings and obtain a Post Approval Amendment (PAA).
Get a printable version.
Project Completion Close-out Checklist
- Certification: At the completion of the project and following removal of the installation, Applicant may submit a certificate of removal, which may be audited.
Get a printable version.