Summary of Filing Period and Calendar for Extension of Time Applications
Filing Period | File on SOC for Extension of Time | File on SOC for Extension of Time and Request Waiver1 | File on SOC2 for Amendment and Request Waiver1 | File on BZ as New Application |
---|---|---|---|---|
Within one (1) year before or within thirty (30) days after the expiration of time to complete construction | ||||
(a) Pre-1961 Use Grant | Yes | No | No | No |
(b) Pre-1961 Bulk Grant | Yes | No | No | No |
(c) Post-1961 Variance | Yes | No | No | No |
(d) Post-1961 Special Permit | Yes | No | No | No |
(e) Transient Parking Waiver | Yes | No | No | No |
More than one (1) year before or less than two (2) years after the expiration of time to complete construction | ||||
(a) Pre-1961 Use Grant | No | Yes | No | Yes |
(b) Pre-1961 Bulk Grant | No | Yes | No | Yes |
(c) Post-1961 Variance | No | Yes | No | Yes |
(d) Post-1961 Special Permit | No | Yes | No | Yes |
(e) Transient Parking Waiver | No | Yes | No | No |
More than two (2) years after but less than four (4) after the expiration of time to complete construction | ||||
(a) Pre-1961 Use Grant | No | No | Yes | No |
(b) Pre-1961 Bulk Grant | No | No | Yes | No |
(c) Post-1961 Variance | No | Yes | No | Yes |
(d) Post-1961 Special Permit | No | Yes | No | Yes |
(e) Transient Parking Waiver | No | No | Yes | No |
More than four (4) years after the expiration of time to complete construction | ||||
(a) Pre-1961 Use Grant | No | No | Yes | Yes |
(b) Pre-1961 Bulk Grant | No | No | Yes | Yes |
(c) Post-1961 Variance | No | No | No | Yes |
(d) Post-1961 Special Permit | No | No | No | Yes |
(e) Transient Parking Waiver | No | No | Yes | No |
Within one (1) year before or thirty (30) days after the expiration of time to obtain a certificate of occupancy | ||||
(a) Pre-1961 Use Grant | Yes | No | No | No |
(b) Pre-1961 Bulk Grant | Yes | No | No | No |
(c) Post-1961 Variance | Yes | No | No | No |
(d) Post-1961 Special Permit | Yes | No | No | No |
(e) Transient Parking Waiver | Yes | No | No | No |
More than one (1) year before or more than thirty (30) days after the expiration of time to obtain a certificate of occupancy | ||||
(a) Pre-1961 Use Grant | No | Yes | No | Yes |
(b) Pre-1961 Bulk Grant | No | Yes | No | Yes |
(c) Post-1961 Variance | No | Yes | No | Yes |
(d) Post-1961 Special Permit | No | Yes | No | Yes |
(e) Transient Parking Waiver | No | Yes | No | No |
This table is intended to serve as a summary. Please see the full text of the associated rule for all requirements.