Service Levels

The Department regularly updates this information to serve you better. Service Level projections are approximate and are subject to change. For requests submitted today, expect the following levels of service: from the units indicated.

NOTE: All times are in business days

Click a topic, or press the enter key on a topic, to reveal its answer.
Printer version.

Boilers

NOTE: General inquiry Service Levels for Boilers are two (2) business days.

Bronx: 3 Day(s)
Brooklyn: 3 Day(s)
Manhattan: 3 Day(s)
Queens: 3 Day(s)
Staten Island: 3 Day(s)

Elevators

NOTE: General inquiry Service Levels for Elevators are two (2) business days.

Bronx: 17 Day(s)
Brooklyn: 20 Day(s)
Manhattan: 30 Day(s)
Queens: 20 Day(s)
Staten Island: 7 Day(s)

Inspection Lead Time

Bronx

Builder's Pavement Plan (BPP): 1 Day(s)
Construction: 5 Day(s)
Electrical: 5 Day(s)
House Connection: 1 Day(s)
Plumbing: 2 Day(s)
Sustainability: 2 Day(s)

Brooklyn

Builder's Pavement Plan (BPP): 1 Day(s)
Construction: 2 Day(s)
Electrical: 3 Day(s)
House Connection: 1 Day(s)
Plumbing:  2 Day(s)
Sustainability: 2 Day(s)

Manhattan

Builder's Pavement Plan (BPP): 1 Day(s)
Construction: 4 Day(s)
Electrical: 5 Day(s)
House Connection: 1 Day(s)
Plumbing: 3 Day(s)
Sustainability: 2 Day(s)

Queens

Builder's Pavement Plan (BPP): 1 Day(s)
Construction: 4 Day(s)
Electrical: 3 Day(s)
House Connection: 1 Day(s)
Plumbing: 2 Day(s)
Sustainability: 2 Day(s)

Staten Island

Builder's Pavement Plan (BPP): 1 Day(s)
Construction: 7 Day(s)
Electrical: 3 Day(s)
House Connection: 1 Day(s)
Plumbing: 2 Day(s)
Sustainability: 2 Day(s)

Review for Sign-off/Rejection Turnaround Time

Bronx

Builder's Pavement Plan (BPP): 1 Day(s)
Construction: 1 Day(s)
Electrical: 2 Day(s)
House Connection: 1 Day(s)
Plumbing: 1 Day(s)

Brooklyn

Builder's Pavement Plan (BPP): 1 Day(s)
Construction: 1 Day(s)
Electrical: 2 Day(s)
House Connection: 1 Day(s)
Plumbing: 1 Day(s)

Manhattan

Builder's Pavement Plan (BPP): 1 Day(s)
Construction: 1 Day(s)
Electrical: 2 Day(s)
House Connection: 1 Day(s)
Plumbing: 1 Day(s)

Queens

Builder's Pavement Plan (BPP): 1 Day(s)
Construction: 1 Day(s)
Electrical: 2 Day(s)
House Connection: 1 Day(s)
Plumbing: 1 Day(s)

Staten Island

Builder's Pavement Plan (BPP): 1 Day(s)
Construction: 1 Day(s)
Electrical: 2 Day(s)
House Connection: 1 Day(s)
Plumbing: 1 Day(s)

Service Levels Tracker

We are currently making updates to our interactive service level dashboard, while this work is ongoing please see the latest 2022 Q1 service level data.

At the Department of Buildings, we pride ourselves on safety, transparency, and efficiency. The Service Levels Tracker allows property owners and the public to better understand DOB timelines. Our goal is to help every New Yorker understand the impact our inspections and approvals have on the timelines of their projects. With this online tool New Yorkers are allowed to see the average wait times for DOB services all in one place, with clear explanations of the different DOB metrics. . This creates an environment where the property owner and construction professional are on the same page as they work together.

The Service Levels Tracker not only helps you plan your project smart; it also helps you plan your project safe. The performance metrics calculate average timelines for Plan Submission Reviews, Inspection Requests, Appointments to Plan Approval, General Customer Service and Construction Safety Compliance. All the metrics used in our Service Levels Tracker are quarterly running averages, updated monthly. Get your project moving by using the Service Levels Tracker.

In addition, the Service Level Tracker assists DOB operationally by spotting our trouble areas. Using this tool, we can improve our efficiency and enhance our customer service. Transparency and accountability being the focal point, we take every opportunity to better serve New Yorkers.

Additional Information

More Information