MAYOR BLOOMBERG AND MTA ANNOUNCE COMPLETION OF FIRST PHASE OF NUMBER 7 SUBWAY EXTENSION

1,000-Ton Tunnel Boring Machine Breaks Through the 34th Street Station Cavern Wall, Completing Train Storage Section between 26th Street and 34th Street along 11th Avenue

City-funded $2.1 Billion Infrastructure Project is First Subway Expansion in Decades

Mayor Michael R. Bloomberg, Deputy Mayor for Economic Development Robert C. Lieber and Metropolitan Transportation Authority Chairman and CEO Jay H. Walder today announced the completion of the first phase of the Number 7 subway extension at the Hudson Yards in Manhattan. The second of two tunnel boring machines has reached the southern wall of the 34th Street Station cavern after mining a combined 2,900 feet from their starting point at 26th Street under 11th Avenue. The $2.1 billion project, funded by the City and managed by the MTA, will help transform the Hudson Yards vicinity into a vibrant 24-hour neighborhood, containing a mix of commercial, residential, retail, open space and recreational uses. In January of 2005, the City Council approved the Bloomberg Administration's plan for re-zoning the Hudson Yards area, including the Eastern Rail Yards. Today, the City Council will vote on the plan for the Western Rail Yards, which would complete the public approvals process for the development of the area.

"It's been a half century since City government expanded its subway system, but that drought will soon be at an end," said Mayor Bloomberg. "Too often, government falls victim to the temptation to abandon long-term infrastructure projects amidst short-term downturns, and that's why big things never get done. The redevelopment of the Hudson Yards has been talked about for decades, but with the expansion of the number 7 line, its potential will finally be realized."

"This week's milestone is a clear indicator that the MTA is delivering on a major expansion project that will increase capacity within our transit system and generate economic growth in a vastly underserved area," said MTA Chairman and CEO Jay H. Walder.  "Much like our joint efforts to improve bus service throughout the city, this partnership between the city and MTA will benefit New Yorkers for generations to come."

"With one of the largest development projects in recent decades on the horizon, the completion of the first phase of the Number 7 Line extension is an important step in making sure that our infrastructure keeps up with the pace of our city," said Council Speaker Christine C. Quinn. "Extending the 7 Line to 34 Street and 11th Avenue will not just open up the Hudson Yards, it will bring New York's next great commercial and cultural center to life and make our sure that our City will continue to thrive."

"Today's announcement of the completion of the first phase of the Number 7 Line extension is a major milestone in the expansion of New York's aged infrastructure," said Rep. Jerrold Nadler. "For too long we have not made the necessary investments to update our transportation network.  This project, which will open the economic potential of the Far West Side, is one of many such projects we need to do to prepare New York for continued growth.  I look forward to the successful completion of this project and future investments in our infrastructure."

"Committing to the expansion of our mass transportation system is only more important to the success of our city in these tough economic times," said Manhattan Borough President Scott M. Stringer. "Development projects like the 7 line expansion and the larger Hudson Yards Redevelopment will bring jobs to New York with real, tangible benefits for our residents.  I want to thank Mayor Bloomberg and the MTA for making possible this milestone on the road to a new and vibrant West Side."

The tunnel boring machines were launched last summer from the underground assembly chamber located at 26th Street.  The first 300 feet of tunneling was complicated by a section of soft ground between 27th and 28th Streets that required a technique called "ground freeze" to reinforce the ground, allowing the machines to pass through as if it were solid rock.  As the tunnel boring machines mine, they place pre-cast concrete lining rings along the excavated tunnel, making up the permanent liner of the finished tunnel.  While the new service will terminate at the new 34th Street station, the tunnels continue to 25th Street to allow for the storage of trains.

One tunnel boring machine has already started mining north of the station cavern toward 42nd Street while the other is being pulled through the cavern and will begin mining in a few weeks.  Tunneling north from 34th Street also presents unique challenges, as track will run under the 8th Avenue Subway, Amtrak/NJ TRANSIT tunnels, tunnels to the former New York Central Line, the Lincoln Tunnel and the Port Authority Bus Terminal and ramps.  Excavation and underpinning of the 8th Avenue Subway line is underway to allow the new tunnels to tie into the existing 7 Line tail tracks at Times Square.

Tunneling will be completed in the Spring of 2010, when work will commence on station entrances and finishes, as well as support facilities such as ventilation and traction power substations. The new service will open in December in 2013 as scheduled.

Construction of the tunnels and the 34th Street Station cavern is being done by S3II Tunnel Constructors, a joint venture of J.F. Shea Construction, Inc., SKANSKA USA Civil Northeast, Inc., and Schiavone Construction Co., Inc.  "The S3II joint venture is very proud to be part of this important project for the MTA and the City," said Jim Marquardt, Project Director for S3II.  The $1.14 billion contract for this work was awarded to S3II in December 2007.

The 7 Line Extension will introduce subway service to an emerging mixed-use community in Midtown West, fostering transit oriented development in one of Manhattan's most underserved and underdeveloped areas.  The City created two local development corporations, the Hudson Yards Infrastructure Corporation, which is contributing $2.1 billion to the project, and the Hudson Yards Development Corporation, which oversees planning and development in the Hudson Yards on behalf of the City.







MEDIA CONTACT:


Stu Loeser / Andrew Brent (Mayor)   (212) 788-2958

Jeremy Soffin / Kevin Ortiz (MTA)   (212) 878-7440




More Resources
Download photo 1
Download photo 2
Download photo 3
Download photo 4