The Department issues a Stop Work Order when Inspectors find hazardous or unsafe work and/or conditions. Stop Work Orders are issued to protect workers, tenants, the public as well as buildings and properties from unsafe conditions.
Full Stop Work Order
Stops all work on a construction site or building, excluding any necessary remedial work to make the site safe.
Partial Stop Work Order
Stops a certain type of work or work on a particular section of the construction site or building. A partial Stop Work Order does not stop all work on the site and certain work is still allowed to continue.
Lifting a Stop Work Order
To lift a Stop Worker Order:
Correct all the violating conditions that resulted in the issuance of the Stop Work Order.
Request a re-inspection from the unit that issued the Stop Work Order to verify that all the violating conditions have been corrected.
Pay any applicable civil penalties
Violating a Stop Work Order
If the Department finds work being done against a Stop Work Order, additional violations may be issued:
First Violation of a Stop Work Order:
| $5,000 |
Any subsequent violation of a Stop Work Order: | additional $10,000 |
The penalties for these violations must be paid before the Stop Work Order can be lifted.