We will complete construction
of Stage 2 and begin repairing Water Tunnel No. 1
Construction on Water Tunnel No. 3, the largest and
most expensive capital project in the city's history,
began in 1970. The 60-mile tunnel was designed in four
stages, beginning at the Hillview reservoir in Yonkers,
traveling through the Bronx, moving south to the tip
of Manhattan and then on to Brooklyn and Queens.
Stage 1, which serves northern Manhattan and parts
of the Bronx, was projected to cost $238 million and
be completed within eight years. It finally opened in
1998-at a cost of a billion dollars. (See case study
on following page: Water Tunnel No. 3)
Stage 2 is currently under construction in Brooklyn,
Queens, and Manhattan and will begin delivering water
in two stages: the Brooklyn/Queens leg will open in
2009, with the Manhattan leg following in 2012. Although
Stage 2 will not provide full redundancy for the in-city
distribution, its completion will enable Water Tunnel
No. 1 to be shut down for repairs, which are estimated
to cost $365 million.
Progress (as of 4/22/08):
The City completed the tunneling of the Brooklyn/Queens
leg in 2001 and the construction of shafts on this leg
is significantly complete. DEP completed the mining
of the Manhattan leg of Water Tunnel No. 3 in 2006.
Construction of the shafts and the lining of the Manhattan
leg continues. Activation is scheduled for 2013.
We will complete Stages 3 and 4 of Water Tunnel
No. 3
The third stage of the water tunnel, also known as the
Kensico-City Tunnel (KCT), will extend from the Kensico
Reservoir to the valve chamber in the Bronx. This 16-mile
section, currently in the planning stage will provide
critical redundancy between the Kensico and Hillview
reservoirs. Although this stage is estimated to cost
between $4 and $6 billion, just $239 million is currently
included in the 10-year plan.
Stage 4 of Water Tunnel No. 3 will be 14 miles long
and run from the valve chamber in the Bronx under the
East River into Queens. It will provide more distribution
in Queens and provide full coverage during the eventual
shutdown and repair of Water Tunnel No. 2
Progress (as of 4/22/08):
Preliminary design (10%) for the construction of Stage
3, also known as the Kensico City Tunnel, is nearly
complete. Given the long-term nature of Stage 4, design
has not yet started. |