We will expand our supply
potential through increased efficiency
Restore groundwater use in Jamaica, Queens
In 1996, DEP bought the Jamaica Water Supply system,
which at its peak supplied 65 mgd to southeast Queens.
Pumps extracted groundwater and distributed it across
the borough in contrast to our upstate system which
relies on gravity 95% of the time. Another difference
was flavor: the ground water tasted different from our
upstate supply.
Today, only one mgd from this system is circulated
throughout southeast Queens, primarily because of the
ample supply of cheaper surface water available from
upstate. But while groundwater is far more expensive
to clean and distribute, it has several advantages.
The supply is constant and not subject to drought. Expanding
this water source will diversify our supply, providing
important redundancy. That is why DEP will begin upgrading
the groundwater system in southeast Queens and begin
construction on an enhanced treatment plant between
2011 and 2012. By 2016, the Jamaica system will provide
an additional 10 mgd.
New Croton Aqueduct
As discussed above, the construction of the Croton Filtration
Plant, as well as improvements to the New Croton Aqueduct,
will ensure the safe and reliable delivery of up to
290 mgd of water from the Croton water supply system.
Alternative connections to the reservoir for emergency
use
Today, the New Croton Aqueduct is the only way to bring
water from the Croton Watershed into the city. But the
Delaware Aqueduct passes directly through the Croton
Watershed; strong pumps could force the water into the
Delaware Aqueduct below the point of the leak described
earlier.
Although we currently have hydraulic pumps in place,
they lose three gallons of water for every gallon successfully
transferred. Upgrading these pumps to more efficient
models will enable us to convey 125 mgd of Croton Water
through the Delaware Aqueduct. We expect these new pumps
to be operational by 2011 and cost $62 million.
Progress (as of 4/22/08):
DEP completed the environmental review of the Cross
River Pump Station, which will allow the transfer of
60 million gallons per day (mgd) from the Croton Watershed
to the Delaware Aqueduct below the location of the leak,
and has released the bid to obtain construction contracts.
The construction bids were due in March and DEP anticipates
the contractor to be on board by the Fall of 2008. Design
is progressing for the Croton Falls Pump Station, which
will allow the transfer of 180 MGD from the Croton Watershed
to the Delaware Aqueduct below the location of the leak.
DEP will release the bids to obtain construction contracts
for the Croton Falls Pump Station in 2010. |