Activities from 10/12/09 –
10/16/09
Install floor tile on north- and south-bound platforms
(night hours)
Install station house ceiling
Form and pour railing curbs at
station house
Install northern and remove southern retaining wall at 94/95
Street Mall
Install stair treads at east and west station house stairs
Activities from 10/19/09 –
10/23/09
Install floor tile on north- and south-bound platforms
(night hours)
Install station house ceiling
Install northern and remove
southern retaining wall at 94/95 Street Mall
Install stair treads at east
and west station house stairs