On May 2, 2008, the Department of City Planning acting on behalf of the City Planning Commission as lead agency issued a Notice of Completion (NOC) for the Draft Environmental Impact Statement (DEIS) in connection with the East Village/Lower East Side Rezoning. With support from Community Board 3 to complete the environmental review process, the Department prepared this DEIS, which followed the issuance of a Final Scope of Work on February 13, 2008, a public scoping meeting held on June 25, 2007, and subsequent public comment period. The DEIS reflects public comments made during the scoping process and incorporates an expanded Inclusionary Housing alternative as a direct response.
On May 5, 2008, following the issuance of this NOC, the Department of City Planning certified the Uniform Land Use Review Procedure (ULURP) application (C080397 ZMM) for the East Village/Lower East Side Rezoning and referred the related non-ULURP zoning text amendment (N 080398 ZRM) to begin the formal public review process.
| Milestone |
Date |
Department of City Planning Certification |
5/5/2008 |
| Community Board 3 Review |
Must be completed by 7/14/2008 |
| Manhattan Borough President Review |
30 Days |
City Planning Commission Review
|
60 Days |
| City Council Review |
50 Days |
For more information about this proposal please contact the Department of City Planning, Manhattan Office, at 212 720-3480.
Overview | Existing Context and Zoning | Proposed Zoning | Environmental Review | Public Review
Items
accompanied by this symbol require the free
Adobe Acrobat Reader.
|